Road construction contracted

November 1, 2014

Sedgeley and the City of Nacala in association with local civil contractors sign an agreement to begin the construction of the Road. Road Construction is anticipated to begin in February 2015.

Local Contractors, Local Materials

October 1, 2014

Sedgeley Creates a road Building plan to make use of Local Contractors, Local Materials in association with the City of Nacala.

Road plan approved

August 1, 2014

The New Roads Plan is presented to ANE and The Ministry of Development and Planning. The Road is approved by both parties and GAZEDA Investment Counsel endorses the road program.

New road plan submitted

July 1, 2014

Sedgeley Presents Nacala with the road development plan that will be the first phase of the New Nacala Development zone. This road plan strategically plans a new road from the Nacala Airport to the Port running directly through the Nacala Business Campus

Memorandum of Understanding

July 1, 2014

Sedgeley Signs a Memorandum of Understanding with the City of Nacala to assist with the roads project and facilitate the building and design of the road.

Nacala Business Campus redesign

June 1, 2014

Sedgeley collaborates with the City of Nacala to redesign the entire precinct area around the Nacala Business Campus. This precinct is a 250Ha area that will link the existing road network in Nacala to a new road network that has been adopted as the blueprint for the New Nacala Development Zone.

New road design

May 1, 2014

Sedgeley redesigns the Site to allow the road to pass through the middle of the site, Sedgeley gain approval from The City of Nacala for the new Road path

Environmental impact assessment approval

April 1, 2014

Sedgeley obtains the Environmental Impact Assessment approvals for the project.

Demographic study

March 1, 2014

Sedgeley Concludes a Demographic Study on the Site and Nacala. This is a successful study and indicated a population of over 1 million people who are subserviced in the greater Nacala catchment area.

Environmental study

February 1, 2014

Nampula Provincial Environmental Department require a full study on the site, and the site is a Categorised a B sensitivity site.

Land compensation

December 1, 2013

Sedgeley successfully negotiates the compensation with the local farming community and clears the land.

Successful application for construction licence

September 1, 2013

Sedgeley Developments submits a successful application to obtain the required Construction Licence

Sedgeley negotiates land parcel in City of Nacala

July 1, 2013

Sedgeley Developments successfully negotiates a land parcel in The City of Nacala, and works in collaboration with the City of Nacala to bring about a new business centre in Nacala – The Nacala Business Campus

Sedgeley Developments Mozambique, LDA formed

June 1, 2013

Sedgeley Developments Mozambique, LDA is formed with the intention of creating high Quality accessible developments in Mozambique

Sedgeley pegs and secures site

January 11, 2013

Sedgeley pegs the site and secures the site by way of Concrete columns placed at 50m intervals around the site demarcating the site. This ensures that there is no civil or private land within the site boundary not previously anticipated Sedgeley Developments submits the EIA scoping report for consideration by the Provincial Environmental Department.

Study of civil requirements

January 10, 2013

Sedgeley Surveys the site and contracts engineers to conduct an initial study of civil requirements for the Site.